Hut 8 describes Beacon Point as a 525-acre AI campus in Nueces County, Texas, with 1,000 megawatts of utility capacity. That figure measures the planned electricity supply to the campus, rather than computing equipment alone. In its July lease announcement, the company said two leases covered 704 megawatts of IT capacity, with Phase 2 accounting for 352 megawatts supported by 500 megawatts of utility capacity.
Hut 8’s announcement came after The Texas Tribune reported Nov. 17 that environmental permit reviews had resumed, quoting TCEQ spokesperson Laura Lopez saying the agency had returned to its normal permit-review process. In an Oct. 19 letter, TCEQ said it had paused issuing permits related to construction or development of infrastructure directly supporting data centers under Gov. Greg Abbott’s Sept. 21 directive.
The grid review is a separate process. ERCOT, the Electric Reliability Council of Texas, said in its Nov. 5 update that detailed analysis was underway and it was targeting Dec. 10 for publication of its final community-impact report. Its August presentation separately described a pause on approvals to energize large data centers until ERCOT completed its Batch Zero eligibility checks. Those checks concern participation in a transitional study of large electricity users’ effects on grid reliability.
Hut 8’s July announcement targeted the first Phase 2 data-hall delivery for the second quarter of 2028. It described the tenant as the same high-investment-grade company leasing Phase 1, without naming it in that release.