Hut 8 Says Beacon Point Phase 2 Cleared for Construction

source-logo  thedefiant.io 23 m
image

Hut 8 said it received a Texas environmental authorization for the second phase of its Beacon Point AI target="__blank" rel="noopener noreferrer ">Nov. 24 announcement, Hut 8 said the Texas Commission on Environmental Quality, or TCEQ, had granted a Notice of Intent authorization for Phase 2 and that site preparation was underway. The company described the campus as “cleared for construction.”

The company’s construction-clearance claim does not establish permission to draw electricity from the grid. The precise permit program and conditions attached to the Phase 2 authorization have not been independently confirmed. Hut 8’s announcement identifies it only as a Notice of Intent authorization, not an ERCOT approval to energize the site.

View post on X

Know when your
coins move

Alerts, real-time prices, and market news — all in one app
qr-code Point your phone camera to install
4.8 based on 40K reviews in the App Store and Google Play

Hut 8 describes Beacon Point as a 525-acre AI campus in Nueces County, Texas, with 1,000 megawatts of utility capacity. That figure measures the planned electricity supply to the campus, rather than computing equipment alone. In its July lease announcement, the company said two leases covered 704 megawatts of IT capacity, with Phase 2 accounting for 352 megawatts supported by 500 megawatts of utility capacity.

Hut 8’s announcement came after The Texas Tribune reported Nov. 17 that environmental permit reviews had resumed, quoting TCEQ spokesperson Laura Lopez saying the agency had returned to its normal permit-review process. In an Oct. 19 letter, TCEQ said it had paused issuing permits related to construction or development of infrastructure directly supporting data centers under Gov. Greg Abbott’s Sept. 21 directive.

The grid review is a separate process. ERCOT, the Electric Reliability Council of Texas, said in its Nov. 5 update that detailed analysis was underway and it was targeting Dec. 10 for publication of its final community-impact report. Its August presentation separately described a pause on approvals to energize large data centers until ERCOT completed its Batch Zero eligibility checks. Those checks concern participation in a transitional study of large electricity users’ effects on grid reliability.

Hut 8’s July announcement targeted the first Phase 2 data-hall delivery for the second quarter of 2028. It described the tenant as the same high-investment-grade company leasing Phase 1, without naming it in that release.

thedefiant.io