en
Back to the list

CleanSpark secures $2.276 billion in bonds for Meta-leased Sandersville campus

source-logo  cryptobriefing.com 11 m
image

CleanSpark has closed a $2.276 billion private placement of senior secured notes to build a 175 MW data center campus in Sandersville, Georgia. The tenant lined up for the entire facility is a subsidiary of Meta Platforms.

For a company best known for mining Bitcoin, that is a notable change of address. The deal lands as CleanSpark reports a fiscal year with falling revenue and a net loss of nearly a billion dollars.

The bond deal, piece by piece

The transaction closed on September 25, 2026. The notes carry a 7.875% coupon and mature on October 1, 2031.

Know when your
coins move

Alerts, real-time prices, and market news — all in one app
qr-code Point your phone camera to install
4.8 based on 40K reviews in the App Store and Google Play

They were sold at 98.5% of par, which pushes the effective yield to around 8.25%.

The borrower is CSDC Finance I, LLC, a wholly-owned CleanSpark subsidiary.

Investor appetite was strong. The offering reportedly attracted approximately $10 billion in orders, a book several times larger than the amount raised.

Interest payments are set to start in April 2027. Principal amortization is scheduled to begin after construction, structured to keep debt service coverage ratios on target.

Why lenders lined up

The answer is the tenant. The Sandersville campus is fully leased for 20 years to Anviran, LLC, a Meta Platforms subsidiary.

That lease represents approximately $6.6 billion in contracted revenue, with a 3% annual escalator built in. The project is expected to produce around $330 million in net operating income each year.

The first data hall is scheduled for delivery in November 2027.

A rough year in the mining business

For the fiscal year ended September 30, 2026, the company reported revenue of $576.5 million, down 25% year-over-year.

Net loss came in at $987.1 million. The company attributed most of that to impairments on its Bitcoin holdings.

CleanSpark mined 7,253 $BTC during the fiscal year at an average hashrate of 36 EH/s.

The company ended the year with approximately $1.3 billion in liquidity. That included 13,530 $BTC valued at around $1.13 billion, plus $204.8 million in cash.

From hashrate to high-performance computing

The difference lies in the revenue profile. Mining income depends on Bitcoin’s price, network difficulty, and the halving schedule. A long-term data center lease pays an agreed amount with a built-in annual increase.

Projected annual net operating income of around $330 million would equal well over half of CleanSpark’s total fiscal 2026 revenue. That is a single campus measured against an entire year of the company’s existing business.

What this means

There are real risks. The notes carry a coupon near 8%, and interest starts flowing out in April 2027, months before the first data hall is due in November 2027.

Construction timelines for data centers can slip, and any delay would stretch the gap between paying interest and collecting rent. The amortization structure is built to protect coverage ratios, but it assumes the build stays on track.

The core mining business also remains exposed. A net loss of $987.1 million and a 25% revenue drop show how quickly Bitcoin price moves flow through the income statement, and the company’s liquidity is still heavily weighted toward its $BTC holdings.

cryptobriefing.com