A publicly traded company that sold off its entire bitcoin treasury to fund a move into artificial intelligence is now warning investors that it may not have enough money to complete the project.
Hyperscale Data (GPUS), which previously operated bitcoin mining facilities, said in a regulatory filing Wednesday that it needs another $74.8 million between November and March to finish building infrastructure for an AI customer at its Michigan data center.
The company had just $17 million in unrestricted cash at the end of September, against $231 million in current liabilities. Its short-term liabilities exceeded current assets by $128 million. Unrestricted cash had fallen by more than half from $36.8 million at the end of June.
The company announced last week that it had sold its remaining 211 $BTC for roughly $16 million, bringing total bitcoin sales since late July to approximately 1,113 $BTC worth roughly $74 million.
Management said existing funds and available financing would not be sufficient to cover its planned spending and obligations over the next 12 months, raising "substantial doubt" about its ability to continue operating. The company issued a similar warning in August.
Hyperscale shares closed Wednesday up 1.75% at 15.7 cents. The filing came out after the close.
Pivot to AI
The warning comes as Hyperscale attempts to turn a former bitcoin mining operation in Dowagiac, Michigan, into a facility serving AI computing companies.
In June, the company signed a contract with an unnamed California-based AI infrastructure provider for 20 megawatts of computing capacity. Hyperscale has promoted the agreement as potentially worth $1.2 billion, although that figure assumes the customer exercises two five-year extensions beyond the initial 10-year term and the company fulfills its obligations.
The project is expected to cost $122.1 million to construct and equip, with $47.3 million paid through October. Hyperscale is targeting its first 10 megawatts of capacity for December and another 10 megawatts by the end of March.
The filing said management was considering additional equity and debt financing, asset sales and other transactions to cover its obligations. Meanwhile, its existing program for selling common shares directly into the market is currently suspended.
Hyperscale recorded a net loss of approximately $62 million in the first nine months of 2026.
As such, the immediate construction timetable leaves little room for delay. The company expects to spend the remaining $74 million on the Michigan project by March, with the first phase scheduled to become available to its AI customer in December.
coindesk.com