Soluna Holdings said on Sept. 8 that it energized the final 14 megawatts at Project Kati 1 in Texas, completing the 83 MW Bitcoin-hosting site. The milestone lifts the company’s total operating capacity to approximately 206 MW and closes the first phase of a planned 166 MW computing campus.
In its project update, Soluna also said the Electric Reliability Council of Texas conditionally classified the entire Kati campus as Base Load in its Batch Zero interconnection process. That designation includes Kati 1 and the planned 83 MW Kati 2 expansion.
Final 14 MW completes the first phase
Soluna said every phase of Kati 1 was delivered on schedule and that infrastructure costs remained on budget. Energization began in February after ERCOT approval. The 48 MW Kati 1A section was completed on April 1 and filled by Galaxy Digital, while the remaining 35 MW came online in stages through the summer.