Crusoe said Friday it is developing a new 900 megawatt AI factory campus in Abilene, Texas, to support Microsoft, expanding one of the largest AI infrastructure hubs in the US as hyperscalers race to secure power and data center capacity for next-generation AI workloads.
The new campus will sit next to Crusoe’s existing Abilene infrastructure and include two buildings plus an onsite power plant designed to support grid resilience. Crusoe said the addition will bring the site’s total projected capacity to 2.1 gigawatts, with land clearing already underway and the first building expected to be energized in mid 2027.
The move builds on Crusoe’s earlier Abilene expansion. In March 2025, the company said it was increasing the campus to 1.2 gigawatts across eight buildings, with the second phase then expected to finish in 2026. Crusoe has described the first Abilene phase as a 200 megawatt initial build that scaled into one of the biggest AI infrastructure developments in the country.