The offering is set to close alongside MARA’s acquisition of Long Ridge Energy & Power LLC, targeted for around November 27, 2026. If the acquisition is not completed by that date, the notes will not close.
The acquisition carries an enterprise value of approximately $1.5 billion, subject to adjustments. MARA first announced the deal in late April 2026.
The centerpiece is a natural-gas plant in Hannibal, Ohio. CoinDesk describes it as a 485-megawatt facility, and deal disclosures put its nameplate capacity at 505 MW. Nameplate capacity is the theoretical maximum output, so the gap between the two figures reflects different ways of measuring the same plant.
Regulators have already signed off. The Federal Energy Regulatory Commission approved the transaction on November 4/5, 2026, which removes one of the bigger hurdles standing between MARA and closing.
Selling Bitcoin to clean up the balance sheet
The bond is only part of the financing. After the end of Q3 2026, MARA sold 13,597 $BTC for about $1.1 billion, at an average price of roughly $81,039.
Of the sale proceeds, MARA used $750 million to repay term loans backed by its Bitcoin holdings. The repayment freed 17,477 $BTC that had been pledged as collateral.
The math is notable. MARA sold 13,597 $BTC but unlocked 17,477 $BTC from collateral obligations. In other words, the company gave up some Bitcoin to regain flexibility over a larger pile of it.
Why a Bitcoin company wants a gas plant
The case for the acquisition comes down to power. According to deal projections, the Long Ridge plant would expand MARA’s operational power capacity by roughly 65%, taking the total to approximately 2.2 GW.
The transaction could also contribute an estimated annualized Adjusted EBITDA of $144 million. That figure is a projection, not a reported result, and it depends on how the assets perform once integrated.
The 1,600-plus acres point to a second ambition. MARA intends to develop the site into an AI computing campus, placing data center capacity next to its own generation source.
What this means
For MARA shareholders, the deal reshapes the risk profile. The company is trading part of its Bitcoin exposure and some loan-backed leverage for a hard energy asset and a secured bond.
Repaying $750 million in Bitcoin-backed loans reduces the risk of forced liquidation during a sharp price drop. On the other hand, MARA takes on new obligations tied to running a gas plant, including fuel costs and operational execution.
The 8.750% interest rate on notes due in 2032 is a fixed cost the business must carry for years. Whether that trade pays off depends heavily on whether the projected $144 million in annualized Adjusted EBITDA materializes.
The Bitcoin sale also deserves attention. A company with a large treasury chose to sell a significant amount of $BTC to deleverage and fund expansion, rather than hold at all costs. Other firms carrying Bitcoin-backed debt may look at MARA’s approach as one template for unwinding encumbered positions.
The near-term item to watch is the closing date. The notes and the acquisition are expected to land together around November 27, 2026, and FERC approval is already in hand.