“Over time, this means transitioning the megawatts in our power portfolio for data center development. Ready-for-service power in the right locations is increasingly scarce and valuable, which in turn forms the basis for the enormous value creation opportunity ahead of us.”
As per the firm’s Q3 report, Riot posted a record quarterly revenue of $180.2 million, up 112.5% from Q3 2024 and net income of $104.5 million compared to a net loss of $154.4 million the year before.
The firm also saw a 27% increase in Bitcoin ($BTC) mining production year-over-year, mining 1,406 $BTC in Q3 and taking its total tally up to 19,287 $BTC, worth over $2.1 billion at current prices.
Notably, 90% of Riot’s Q3 revenue came from its Bitcoin mining ventures, indicating the firm still has a significant reliance on digital gold.
Commenting on this, Kane said Riot will continue to maximize potential in Bitcoin mining but will use the funds to support its data center-focused plans.
“We will continue to utilize the opportunity Bitcoin mining brings to secure power and drive strong cash flow that we will leverage to support the ongoing transformation of our overall business,” he said.
Will Bitcoin mining just be a side hustle?
Riot started laying the groundwork for a diversification strategy at the beginning of this year, after the firm paused building out any further Bitcoin mining projects at Corsicana, instead seeking out new opportunities to set up high-performance infrastructure geared toward AI.
Alongside the financial results, the firm announced the “initiation of the core and shell development” of the first two buildings on its Corsicana Data campus in Texas, which will account for a “combined 112 megawatts of critical IT data center capacity.”
Moving forward, the Riot executives outlined their intentions to fill every spare bit of land at Corsicana, eventually turning it into a “1 gigawatt utility-load data center campus.”
“It’s all under the lens of maximizing the value of all of the megawatts that we have, trying to leave no unutilized power while we aggressively build out the data center business. Eventually, we aim to have the entire site be a one-gigawatt utility-load data center campus,” noted CEO Jason Les.